Rebar Calculator

Rebar quantity, weight, stock bars and cost for a slab, beam, column or footing in the US, Pakistan or India, with a bar bending schedule and lap lengths.

Units
Slabs 3/4 to 2 in, footings 3 in (ACI 318). The drawing decides.
Splice allowance on straight bars. 10% is a common estimate.
Cutting offcuts and mistakes. 10% is common.
Per lb. Empty uses the middle of the range.
Steel to order
477 lbWith 10% lap and 10% waste · 0.238 t
Stock bars to buy
36Bars of 20 ft
Total length
713.9 ftCut pieces: 30
Estimated cost
$358Range $286 to $715
Per sq ft
$0.89

Estimate only. The structural drawing decides sizes, spacing, laps and bends.

Plan view, to scale

20 ft20 ft#4 18 in o.c.#4 18 in o.c.Cover 2 in

Main bars (mark A)Distribution bars (mark B)

20 by 20 ft. 15 main bars of #4 every 18 in, 15 distribution bars every 18 in, cover 2 in.

  • Material $286 – $715 · $358
  • Estimated cost $286 – $715 · $358

$0.75/lb · About $1,200 to $1,800 per ton delivered and fabricated, up to $1.50 per lb in small lots. Placing and tying labour is about $500 to $800 per ton. Prices vary by region.

Bar bending schedule

MarkShapeSizeCut lengthQtyWeight
A00#419.67 ft15197 lb
B00#419.67 ft15197 lb
Total (no lap, no waste)394 lb
With lap allowance434 lb
Order weight with waste477 lb

Lap and development length · #4

LengthDistanceIn bar diameters
Lap in tension24.67 in49.3d
Lap in compression15 in30d
Development length18.97 in37.9d
Estimating lap used20 in40d

ACI 318-19 simplified: Grade 60, f′c 4,000 psi, bottom bars, uncoated. Class B lap = 1.3 × development length.

Step by step working

Your numbers worked through, in the same order the calculator uses.

  1. Main bars (along the length): ⌈(240 in − 2 × 2 in) ÷ 18 in⌉ + 1 = 15 bars, each 19.67 ft long.
  2. Distribution bars: ⌈(240 in − 2 × 2 in) ÷ 18 in⌉ + 1 = 15 bars, each 19.67 ft long.
  3. Total length = 15 × 19.67 ft + 15 × 19.67 ft = 590 ft.
  4. Add lap 10%: 590 ft × 1.1 = 649 ft.
  5. Add waste 10%: 649 ft × 1.1 = 713.9 ft.
  6. Weight = 713.9 ft × 0.668 lb per ft = 477 lb (0.238 t).
  7. Stock bars = ⌈713.9 ft ÷ 20 ft⌉ = 36.
  8. Cost = 477 lb × $0.75/lb = $358.

Worked examples

US: 20 × 20 ft slab, #4 at 18 in, 2 in cover

10% lap, 10% waste, 20 ft stock bars, price $0.75/lb.

  1. Main bars (along the length): ⌈(240 in − 2 × 2 in) ÷ 18 in⌉ + 1 = 15 bars, each 19.67 ft long.
  2. Distribution bars: ⌈(240 in − 2 × 2 in) ÷ 18 in⌉ + 1 = 15 bars, each 19.67 ft long.
  3. Total length = 15 × 19.67 ft + 15 × 19.67 ft = 590 ft.
  4. Add lap 10%: 590 ft × 1.1 = 649 ft.
  5. Add waste 10%: 649 ft × 1.1 = 713.9 ft.
  6. Weight = 713.9 ft × 0.668 lb per ft = 477 lb (0.238 t).
  7. Stock bars = ⌈713.9 ft ÷ 20 ft⌉ = 36.
  8. Cost = 477 lb × $0.75/lb = $358.

Pakistan: 4 × 3 m slab, 12 mm at 150 mm, 50 mm cover

5% lap, 5% waste, 12 m stock bars, price Rs 300/kg.

  1. Main bars (along the length): ⌈(3,000 mm − 2 × 50 mm) ÷ 150 mm⌉ + 1 = 21 bars, each 3.9 m long.
  2. Distribution bars: ⌈(4,000 mm − 2 × 50 mm) ÷ 150 mm⌉ + 1 = 27 bars, each 2.9 m long.
  3. Total length = 21 × 3.9 m + 27 × 2.9 m = 160.2 m.
  4. Add lap 5%: 160.2 m × 1.05 = 168.21 m.
  5. Add waste 5%: 168.21 m × 1.05 = 176.62 m.
  6. Weight = 176.62 m × 0.888 kg per m = 156.8 kg (0.157 t).
  7. Stock bars = ⌈176.62 m ÷ 12 m⌉ = 15.
  8. Cost = 156.8 kg × Rs 300/kg = Rs 47,041.

India: 10 × 10 m slab (100 m²), 10 mm at 200 mm, 50 mm cover

5% lap, 3% waste, 12 m stock bars, price ₹58/kg.

  1. Main bars (along the length): ⌈(10,000 mm − 2 × 50 mm) ÷ 200 mm⌉ + 1 = 51 bars, each 9.9 m long.
  2. Distribution bars: ⌈(10,000 mm − 2 × 50 mm) ÷ 200 mm⌉ + 1 = 51 bars, each 9.9 m long.
  3. Total length = 51 × 9.9 m + 51 × 9.9 m = 1,009.8 m.
  4. Add lap 5%: 1,009.8 m × 1.05 = 1,060.29 m.
  5. Add waste 3%: 1,060.29 m × 1.03 = 1,092.1 m.
  6. Weight = 1,092.1 m × 0.617 kg per m = 673.3 kg (0.673 t).
  7. Stock bars = ⌈1,092.1 m ÷ 12 m⌉ = 92.
  8. Cost = 673.3 kg × ₹58/kg = ₹39,052.

Guides

Weight formula

Weight of a round bar per metre = d² ÷ 162.2, with d in millimetres, from steel density 7,850 kg/m³. In the US a quick rule is lb/ft ≈ bar number² ÷ 24. It works for #3 to #9 and is 5 to 7% off for #10, #11 and #14, so the tables use the ASTM A615 values.

Bar size and weight charts

United States, ASTM A615

SizeDia. mmkg/mlb/ft
#39.50.560.376
#412.70.9940.668
#515.91.5521.043
#619.12.2351.502
#722.23.0422.044
#825.43.9732.67
#928.75.063.4
#1032.36.4044.303
#1135.87.9075.313
#144311.3847.65
#1857.320.23913.6

Pakistan, PSQCA

SizeDia. mmkg/mlb/ft
8 mm80.3950.265
10 mm100.6170.414
12 mm120.8880.597
16 mm161.5781.061
20 mm202.4661.657
25 mm253.8532.589
32 mm326.3134.242

India, IS 1786

SizeDia. mmkg/mlb/ft
6 mm60.2220.149
8 mm80.3950.265
10 mm100.6170.414
12 mm120.8880.597
16 mm161.5781.061
20 mm202.4661.657
25 mm253.8532.589
28 mm284.8343.248
32 mm326.3134.242
36 mm367.995.369
40 mm409.8646.629

Lap splice guide

ACI 318-19 sets development length by bar size, grade and concrete. For Grade 60, f′c 4,000 psi, uncoated bottom bars it is about 38d up to #6 and 47d for #7 and up, never under 12 in. A Class B tension lap is 1.3 × that (49d and 62d), and top bars with more than 12 in of concrete below need another 1.3. A compression lap is 0.0005 × fy × d, which is 30d for Grade 60. The 40d used for estimating is a simple allowance.

Pakistani drawings usually call 50d tension laps and 40d compression laps for Grade 60. BCP SP-2007 follows ACI, so the development length is shown as 50d ÷ 1.3, about 38d. Stagger the splices and keep them out of the highest stress zones.

IS 456 Cl. 26.2.1 gives Ld = 0.87 × fy × φ ÷ (4 × τbd). With M20 concrete and HYSD bars τbd is 1.92 N/mm², so Ld is about 47φ for Fe415, 57φ for Fe500 and 62φ for Fe550. Laps of 50d (Fe415) and 60d (Fe500) in tension, 40d in compression, are common practice and never under 30φ. M25 concrete shortens them.

Slab spacing rules of thumb

  • Main bars in a one-way slab: no wider than 3 × the slab thickness (ACI 318: also 18 in at most; IS 456: 300 mm at most). Distribution bars up to 5 × thickness or 450 mm (IS 456).
  • Minimum shrinkage steel: 0.18% of the gross area for Grade 60 (ACI 318), 0.12% for Fe415 and Fe500 (IS 456).
  • Typical house slabs: #3 or #4 at 12 to 18 in in the US, 8 to 10 mm at 125 to 200 mm in Pakistan and India.
  • Chairs or spacers about every 1 m (3 ft) each way keep the mat at its cover. Count them separately, they are not in the weight.

Bar bending schedule (BBS) basics

A BBS lists every bar mark with its shape code, diameter, cut length, quantity and weight. Cut length is the straight length of steel before bending: the outside dimensions minus a deduction at each bend (45° = 1d, 90° = 2d, 135° = 3d, 180° = 4d).

  • 00: Straight: A
  • 11: L-bend: A + B − 2d
  • 21: U-bend: A + B + C − 4d
  • 31: Cranked: A + 0.414 × B (B is the rise of a 45° crank)
  • 51: Stirrup or tie: 2 × (A + B) + 2 × hook − 12d, hook = larger of 6d and 75 mm

Free API

Free JSON endpoint, no key. Please link back to this page when you show the results.

Parameters: market (us, pk, in), mode (slab, beam, column, footing, bbs), L, W, T, sp, sp2, cover, size, lap, waste, stock, grade, units (imp or met), price. Beam: b, h, nTop, nBot, size2, sp3. Column: b, h, nBars. BBS: rows=shape:size:A:B:C:qty;… Dimensions follow units.

Example:

GET https://ivorytool.com/api/rebar?market=pk&mode=slab&L=4&W=3&sp=150&size=12&cover=50&lap=5&waste=5&price=300
Add this calculator to your website

Free to use on any site or blog. Paste this code where you want the calculator to appear. It stays up to date, needs no account, and keeps your visitors' numbers in their own browser.

Preview

Why use our Rebar Calculator?

  • Three markets, three standards US ASTM A615 bar numbers in feet and inches, Pakistan PSQCA and BCP sizes in metric or ft-in, India IS 1786 TMT sizes in metric. Weights, stock lengths, laps and prices change with the market.
  • Slab, beam, column, footing Each member has its own inputs and its own bar counts, with stirrups and ties, dowels and development length where they belong.
  • A full bar bending schedule Add bar marks with shape codes 00, 11, 21, 31 and 51, get the cut length, quantity and weight of each, and download the table as CSV.
  • A drawing to scale The slab plan or the beam and column section is drawn from your numbers, with spacing, cover and splice points, and a text summary for screen readers.
  • Lap and development length Shown in millimetres or inches and as a multiple of bar diameter, for your market and steel grade.
  • Lap and waste allowances Splice and offcut allowances are added, and a note appears when your lap allowance is too small for the bars longer than the stock bar.
  • Cost with a range Material and optional labour in dollars, rupees or INR, with a typical range and your own price on top. The Pakistan note explains why market and official rates differ.
  • The working, shown Every step with your numbers, in the same order as the calculator, so a supplier or engineer can check it.
  • PDF report, free API and embed Print the estimate, call the same maths from your own site without a key, or embed the tool.
  • English, Hindi and Urdu The page flips to right to left in Urdu, and the market is chosen separately from the language. Your numbers stay in your browser.

How to use the Rebar Calculator

Choose the market first: United States, Pakistan or India. It sets the bar sizes and their weights, the stock bar length, the lap rules, the default lap and waste allowances and the price range. Then choose the member: slab, beam, column, footing or a bar bending schedule (BBS).

Slab and footing: bars run both ways. The main bars run along the length and are spaced across the width, so their number is ⌈(width − 2 × cover) ÷ spacing⌉ + 1, and each is the length minus the cover at both ends. The distribution bars follow the same rule the other way. A footing also takes a count of footings and optional L-shaped dowels for the column.

Beam and column: the main bars run the length of the member plus the development length at each end (beam) or a compression lap (column). Stirrups or ties are counted as ⌈length ÷ spacing⌉ + 1, and each is the perimeter inside the cover plus two hooks of 6d or 75 mm, whichever is more, less the bend deductions.

Weight comes from the total length and the bar weight: kilograms per metre are the diameter in millimetres squared divided by 162.2, and US bars use the ASTM A615 pound per foot values. The lap allowance is applied to straight bars, then the waste allowance to everything, and the stock bars are the total length divided by the bar length you buy, rounded up.

This is a quantity estimate. The structural drawing and the local code decide sizes, spacing, cover, laps and bends. Use the tool to price and order, and to check a supplier’s figure.

Metric bar: kg per metre = d² ÷ 162.2   (d in mm, steel density 7,850 kg/m³)
US bar: lb per foot from ASTM A615 (#4 = 0.668). Rough rule: #² ÷ 24 for #3 to #9 only
Bars across a width = ⌈(width − 2 × cover) ÷ spacing⌉ + 1
Bar length = member length − 2 × cover
Total = Σ (bars × length) × (1 + lap %) × (1 + waste %)
Weight = total length × weight per unit length
Stock bars = ⌈total length ÷ stock bar length⌉
Cost = weight × price per unit
Stirrup cut length = 2 × (A + B) + 2 × max(6d, 75 mm) − 12d

Worked examples

United States: a 20 × 20 ft slab with #4 bars at 18 in both ways and 2 in cover. Each way there are ⌈(240 − 4) ÷ 18⌉ + 1 = 15 bars of 19.67 ft, so 590 ft in total. With 10% lap and 10% waste that is 713.9 ft. A #4 weighs 0.668 lb per foot, so the order is about 477 lb, which is 36 bars of 20 ft. At $0.75 per lb the steel costs about $358.

Pakistan: a 4 × 3 m slab with 12 mm bars at 150 mm both ways and 50 mm cover. There are 21 bars of 3.9 m and 27 bars of 2.9 m, 160.2 m in all. With 5% lap and 5% waste that is 176.6 m, about 156.8 kg at 0.888 kg per metre, which is 15 bars of 12 m. At Rs 300 per kg the steel costs about Rs 47,000.

India: a 10 × 10 m slab (100 m²) with 10 mm bars at 200 mm both ways and 50 mm cover. There are 51 bars of 9.9 m each way, 1,009.8 m in all. With 5% lap and 3% waste that is 1,092 m, about 673 kg at 0.617 kg per metre, which is 92 bars of 12 m. At ₹58 per kg the steel costs about ₹39,000.

Good to know

  • It estimates quantity and cost only. The structural drawing decides bar sizes, spacing, cover, laps, bends and anchorage, and it wins over any figure here.
  • Chairs, spacers, tie wire, extra bars at openings and edges, and cranked or bent top steel in a real slab are not included unless you add them as bar marks in the BBS mode.
  • Lap and development lengths are shown for reference. The US figures are the ACI 318-19 simplified values for f′c 4,000 psi and uncoated bottom bars, Pakistan uses common practice (50d and 40d) and India uses IS 456 with M20 concrete. The code and the drawing decide the real values.
  • Prices are indicative ranges, not quotes. Enter your supplier’s price. Pakistani open-market rates are lower than the official Punjab MRS rates, and the range covers both. Indian and US prices vary by city and order size.
  • Bar weight is nominal. Rolled bars can differ by a few percent (IS 1786 allows ±3.5% on weight for small bars), so check the delivery docket.

Questions people ask

How do I calculate rebar for a slab?

Find the clear area inside the cover, count the bars each way as ⌈(width − 2 × cover) ÷ spacing⌉ + 1, multiply each count by the bar length, add lap and waste, then divide by the stock bar length. The slab mode does this and shows each step.

What is the formula for rebar weight?

For a metric bar, kg per metre = d² ÷ 162.2 with d in millimetres, from the density of steel. A 12 mm bar weighs 144 ÷ 162.2 = 0.888 kg per metre. For US bars use the ASTM A615 table: #4 is 0.668 lb per foot.

What is the rebar weight per foot?

ASTM A615: #3 0.376, #4 0.668, #5 1.043, #6 1.502, #7 2.044, #8 2.670, #9 3.400, #10 4.303, #11 5.313, #14 7.650 and #18 13.600 pounds per foot. The size chart on this page also gives kilograms per metre.

What is the TMT bar weight per metre in India?

From IS 1786: 6 mm 0.222, 8 mm 0.395, 10 mm 0.617, 12 mm 0.888, 16 mm 1.58, 20 mm 2.47, 25 mm 3.85, 28 mm 4.83, 32 mm 6.31, 36 mm 7.99 and 40 mm 9.86 kilograms per metre. Bars may differ from nominal by the tolerance in the standard.

How long should a lap splice be?

The code and the drawing decide. In the US a Class B tension lap is 1.3 times the development length, about 49d for bars up to #6 and 62d for #7 and larger at Grade 60 and 4,000 psi. In Pakistan drawings usually call 50d in tension and 40d in compression. In India 50d for Fe415 and 60d for Fe500 are common.

How do I calculate steel for a beam or column?

Enter the length, the section, the main bars and the stirrup or tie size and spacing. Main bars are the length plus anchorage or lap, stirrups are ⌈length ÷ spacing⌉ + 1 and each is the perimeter inside the cover plus hooks. The tool totals the weight and the stock bars.

How do I make a bar bending schedule?

Use the BBS mode. Add a bar mark for each bar type, pick the shape code (00 straight, 11 L-bend, 21 U-bend, 31 cranked, 51 stirrup), the size, the leg lengths and the quantity. The tool gives the cut length and weight of each mark and exports the table as CSV.

Why do Pakistani steel prices differ between sources?

Dealer price sites showed about Rs 255 to 272 per kg in November 2026, while the official Punjab Market Rate System lists about Rs 314 to 321 for Grade 40 and Grade 60, and slightly more with cutting and bending. The official schedule is used for tenders and lags the open market. Enter your dealer quote for a real order.

Part of the guide: Building material calculators: concrete, blocks, bricks, flooring and more

Formulas and text last checked on 21 November 2026. Everything is calculated in your browser, so nothing you enter is sent or stored. Spotted a mistake? Tell us and we will fix it.