Epoxy Flooring Calculator
Rough or porous concrete absorbs more epoxy. Always confirm with the product data sheet. Coverage multiplier 1× on the primer and base coat.
Coverage rates (optional)
Leave blank for the default of your choices. Type the rate from your product data sheet to use it instead.
Kit sizes
Common: 3 or 1.5 gallon epoxy kits, 3 or 1 gallon top coat, 40 lb box or 10 lb bag of flake.
Custom prices (optional)
Leave blank for the 2026 range for your region. A price you type is used as typed, with no regional multiplier. Prices are in US dollars per unit.
- Floor area
- 400 sq ft
- Primer
- 2 kits4.68 gal needed, 6 gal bought
94 sq ft per gal per coat, about 17 mils - Base coat
- 2 kits3.38 gal needed, 6 gal bought
130 sq ft per gal per coat, about 11 mils - Top coat
- 1 kit2.2 gal needed, 3 gal bought
200 sq ft per gal per coat, about 8 mils - Flake
- 1 × 40 lb33.3 lb needed, 40 lb bought
- Material
- $960 to $1,740
- Labor
- $800 to $2,000
- Total installed
- $1,760 to $3,740typical $2,750
$4.40 to $9.35 per sq ft
Rough or porous concrete absorbs more epoxy. Always confirm with the product data sheet. Coverage multiplier 1× on the primer and base coat.
You cannot buy part of a kit, so the quantity bought is always more than the exact amount.
Coverage is a planning rate. Confirm it with the data sheet of the product you buy.
Flake and quartz carry no waste allowance here: the usual rate already assumes some is swept up.
Prices are 2026 planning averages. Local supplier prices may vary.
Floor cross-section
Layers from the slab up: Concrete slab; Moisture vapor primer, 17 mils, 94 sq ft per gal; 100% solids epoxy, 11 mils, 130 sq ft per gal; Flake broadcast, 12 sq ft per lb; Polyaspartic top coat, 8 mils, 200 sq ft per gal.
Material list
Step-by-step build-up
The working with your numbers, layer by layer. It updates as you type.
- Area = 400 sq ft.
- Primer: 400 sq ft × 1 ÷ 94 sq ft per gal × (1 + 10%) = 4.68 gal, which is 2 kits of 3 gal, 6 gal bought.
- Base coat: 400 sq ft × 1 ÷ 130 sq ft per gal × (1 + 10%) = 3.38 gal, which is 2 kits of 3 gal, 6 gal bought.
- Top coat: 400 sq ft × 1 ÷ 200 sq ft per gal × (1 + 10%) = 2.2 gal, which is 1 kit of 3 gal, 3 gal bought.
- Flake: 400 sq ft ÷ 12 sq ft per lb = 33.3 lb, which is 1 of 40 lb, 40 lb bought.
- Material = $960 to $1,740.
- Labor: 400 sq ft × $2.00 to $5.00/sq ft = $800 to $2,000.
- Total installed = $1,760 to $3,740, typical $2,750.
- Cost per sq ft = $4.40 to $9.35.