Each layer can have its own thickness and mix, for example a 4 in base course and a 3 in surface. The tons are added up.
Typical densities. Mix designs vary, so ask your plant for its figure. Plants and labs measure it with tests such as ASTM D2726. Loose HMA is the HMA density divided by the compaction factor.
Off by default. Asphalt weighs the same loose or rolled, so only its volume changes. Turn this on only to match a calculator that multiplies the tons.
These are planning figures, not quotes. Hot mix prices follow crude oil and change from week to week, so replace the price with a quote from your plant.
A driveway base is usually 4 to 6 in of compacted crushed stone, about 100 lb/ft³.
- To order (tons)
- 19.031,000 ft² · 9.26 yd³
- Truckloads
- 1last load 19.03 tons
- Area
- 1,000 ft²
- Compacted volume
- 250 ft³9.26 yd³
- Compacted weight
- 18.13 tons
- Loose volume to haul
- 11.76 yd³× 1.27
- Covered by one ton
- 55 ft²
- Hot mix cost
- $2,28419.03 × $120
- Cost per full truckload
- $2,64022 tons
Small jobs may round up to the plant minimum and to a full truckload.
Hot mix
Square feet covered by one ton at each thickness (inches) for the first layer. The dark bar is your thickness.
Step-by-step working
Worked out with your numbers. It updates as you type.
- Area = 50 × 20 ft = 1,000 ft².
- Volume = 1,000 ft² × (3 in ÷ 12) = 250 ft³.
- Volume in cubic yards = 250 ÷ 27 = 9.26 yd³.
- Compacted weight = 250 ft³ × 145 lb/ft³ ÷ 2,000 = 18.13 tons.
- Loose volume to haul = 9.26 yd³ × 1.27 = 11.76 yd³. The weight stays 18.13 tons, because loose and rolled mix weigh the same.
- Waste (5%): 18.13 × 1.05 = 19.03 tons.
- Truckloads (22 tons per truck): ⌈19.03 ÷ 22⌉ = 1.
- Hot mix cost (at $120 per ton): 19.03 × $120 = $2,283.75.