Earthwork Volume Calculator

Pit or basement

ft

ft

ft

With vertical sides it makes no difference.

0 for vertical sides. 1 means 1 foot of run for each foot of depth (1:1). Your safety rules or engineer set the slope.

Typical figures only. They depend on the soil and its moisture. Use the figure from your soil report or contractor when you have one.

cu yd

Loose soil the truck carries, from your hauler. Leave empty to skip the truck count.

Excavation volume (in the ground)

133.3 cu yd

about 166.7 cu yd loose after digging, 17 truckloads

Size at the bottom
30 ft by 20 ft
Size at the top
30 ft by 20 ft
Volume in the ground (bank)
133.3 cu yd (101.9 m³, 3,600 cu ft)
Volume once dug (loose), with 25% swell
166.7 cu yd (127.4 m³, 4,500 cu ft)
Volume when compacted, with 15% shrink
113.3 cu yd (86.6 m³, 3,060 cu ft)
Soil to refill the hole, compacted (bank measure)
156.9 cu yd (119.9 m³, 4,235 cu ft)
Same soil as loose volume to move
196.1 cu yd (149.9 m³, 5,294 cu ft)
Truckloads of loose soil to haul away
17
Truck capacity used
10 cu yd

Digging 133.3 cu yd in the ground (loam or common earth) gives about 166.7 cu yd of loose soil to move.

Trench

ft

ft

ft

0 for vertical sides. 1 means 1 foot of run for each foot of depth (1:1).

Typical figures only. They depend on the soil and its moisture. Use the figure from your soil report or contractor when you have one.

cu yd

Loose soil the truck carries, from your hauler. Leave empty to skip the truck count.

Trench volume (in the ground)

29.6 cu yd

about 37 cu yd loose after digging, 4 truckloads

Width at the top
2 ft
Cross-section
8 sq ft
Volume in the ground (bank)
29.6 cu yd (22.7 m³, 800 cu ft)
Volume once dug (loose), with 25% swell
37 cu yd (28.3 m³, 1,000 cu ft)
Volume when compacted, with 15% shrink
25.2 cu yd (19.3 m³, 680 cu ft)
Soil to refill the hole, compacted (bank measure)
34.9 cu yd (26.7 m³, 941 cu ft)
Same soil as loose volume to move
43.6 cu yd (33.3 m³, 1,176 cu ft)
Truckloads of loose soil to haul away
4
Truck capacity used
10 cu yd

Digging 29.6 cu yd in the ground (loam or common earth) gives about 37 cu yd of loose soil to move.

Cut and fill

ft

ft

ft

The average of your level readings, on the same datum as the finished level.

ft

Typical figures only. They depend on the soil and its moisture. Use the figure from your soil report or contractor when you have one.

cu yd

Loose soil the truck carries, from your hauler. Leave empty to skip the truck count.

Cut volume (in the ground)

88.9 cu yd

about 111.1 cu yd loose after digging, 12 truckloads

Area
2,400 sq ft
Average depth of cut
1 ft
Volume in the ground (bank)
88.9 cu yd (68 m³, 2,400 cu ft)
Volume once dug (loose), with 25% swell
111.1 cu yd (85 m³, 3,000 cu ft)
Volume when compacted, with 15% shrink
75.6 cu yd (57.8 m³, 2,040 cu ft)
Truckloads of loose soil to haul away
12
Truck capacity used
10 cu yd

Digging 88.9 cu yd in the ground (loam or common earth) gives about 111.1 cu yd of loose soil to move.

Earthwork Volume Calculator by Ivorytool, free tools that run in your browser.